On Track
In progress:
Live from Jira · AH · refreshes every minute
Read-only share link
/epic/bayadaAnyone with this link sees this dashboard only — view access, no editing.
Progress
2%
2 of 124 tasks complete
Days until go-live
—
Go-live Oct 16
Next target date
Sep 18
Discovery & Requirements
Project Timeline
SepOct
Discovery & Requirements
Target Sep 18
Technical Configuration
Target Sep 25
Testing & Validation
Target Sep 26
Training & Change Management
Target Oct 2
Pre-Launch Preparation
Target Oct 9
Go-Live
Target Oct 16
Optimization & Expansion
Target Oct 23
Project plan
Complete onsite workflow observation at Central Delaware Nursing (CDN)Completed
Complete onsite workflow observation at Washington Township (WT)Completed
Complete onsite workflow observation at Tampa (TAM) — Aug 17-18Not Started
Complete onsite workflow observation at Orlando (OAN) — Aug 19-20Not Started
Complete onsite workflow observation at Mechanicsburg Pediatrics (MBP) — Aug 25-26Not Started
Complete onsite workflow observation at Lancaster (LAN) — Aug 27-28Not Started
Document corporate compliance items list (required across all offices)Not Started
Document office-specific compliance items (variations by state/location)Not Started
Map compliance items to Statewise credential tab fieldsNot Started
Identify which items are tracked in Statewise vs. Workday vs. LMSNot Started
Confirm which credentials are hard blockers vs. soft requirementsNot Started
Define notification escalation cadence per credential typeNot Started